We are now in week 37 of the 78 week building project to create our new home at Castle Mills. Whilst work to prepare the building for the construction phase continues, key elements of the building are starting to take shape. The brickwork remedial work, roof refurbishment and forming of lead gutters are ongoing.

The window refurbishment is continuing off-site, while some new windows have already been installed.

The cupula is now back on site and being reinstalled. All of these are contributing to the transformation of the exterior of the building.

The steelwork structure for the extension adjoining the west courtyard, which will house our cafe, is now under construction and starting to give a sense of how this space will look.

Over the next few weeks, the entrance to Dundee Street will be opened up to reveal how the new entrance will look for our visitors in 2019. Watch this space for further updates in the coming weeks!